Yocto Project Status WW26'19

DISCUSSION [email protected] 2 participants 2 messages Jun 25, 2019

lore
Share & tools
lore
#0 lore raw

Current Dev Position: YP 2.8 M2

Next Deadline: YP 2.8 Milestone 2 Cutoff July 14th, 2019

SWAT Team Rotation:

* SWAT lead is currently: Ross
* SWAT team rotation: Ross -> Amanda on June 28, 2019
* SWAT team rotation: Amanda -> Chen on July, 5, 2019
* <https://wiki.yoctoproject.org/wiki/Yocto_Build_Failure_Swat_Team>
https://wiki.yoctoproject.org/wiki/Yocto_Build_Failure_Swat_Team

Next Team Meetings:

* Bug Triage meeting Thursday June 27th at 7:30am PDT (
<https://zoom.us/j/454367603> https://zoom.us/j/454367603)
* Monthly Project Meeting Tuesday July 2nd at 8am PDT (
<https://zoom.us/j/990892712> https://zoom.us/j/990892712)
* Twitch - Next event is Tuesday 9th July at 8am PDT (
<https://www.twitch.tv/yocto_project> https://www.twitch.tv/yocto_project)

Key Status/Updates:

* 2.8 M1 has been released.
* Mailing lists issues are continuing to be worked on as a top
priority.
* We have a new "newcomer" bug category which are bugs suited to
someone new to the project. These can be seen here:
<https://wiki.yoctoproject.org/wiki/Bug_Triage#Newcomer_Bugs>
https://wiki.yoctoproject.org/wiki/Bug_Triage#Newcomer_Bugs
* Several key reproducibility fixes have merged, thanks Joshua!
* The autobuilder has suffered stability issues with its NFS setup,
seemingly related to the increased load from the new servers. We're monitoring changes, hoping they fix the issue.
* We had significant problems with the versioning of libcrypt in
recent distros which resulted in the need for a new uninative release. This fixes autobuilder builds.

Planned Releases for YP 2.8:

* M2 Cutoff 14th July
* M2 Release 26th July
* M3 Cutoff (Feature Freeze) 25th Aug
* M3 Release 6th Sept
* M4 Cutoff 30th Sept
* 2.8 (M4) Final Release 25th Oct

Planned upcoming dot releases:

* YP 2.7.1 (Warrior) is planned for build imminently now that 2.8 M1
is done but is pending the new uninative changes.
* YP 2.6.3 (Thud) is intended for build after 2.7.1 is complete and
before 2.8 M2

Tracking Metrics:

* WDD 2482 (last week 2479) (
<https://wiki.yoctoproject.org/charts/combo.html>
https://wiki.yoctoproject.org/charts/combo.html)
* Poky Patch Metrics

* Total patches found: 1509 (last week 1511)
* Patches in the Pending State: 638 (42%) [last week 641 (43%)]

Key Status Links for YP:

<https://wiki.yoctoproject.org/wiki/Yocto_Project_v2.8_Status>
https://wiki.yoctoproject.org/wiki/Yocto_Project_v2.8_Status

<https://wiki.yoctoproject.org/wiki/Yocto_2.8_Schedule>
https://wiki.yoctoproject.org/wiki/Yocto_2.8_Schedule

<https://wiki.yoctoproject.org/wiki/Yocto_2.8_Features>
https://wiki.yoctoproject.org/wiki/Yocto_2.8_Features

The Status reports are now stored on the wiki at:
<https://wiki.yoctoproject.org/wiki/Weekly_Status>
https://wiki.yoctoproject.org/wiki/Weekly_Status

[If anyone has suggestions for other information you'd like to see on this weekly status update, let us know!]

Thanks,

Stephen K. Jolley

Yocto Project Project Manager

* Cell: (208) 244-4460

* Email: [email protected]
<mailto:[email protected]>

#1 lore raw
Quoted 5 lines · On 6/25/19 10:22 AM, [email protected] wrote:

Current Dev Position: YP 2.8 M2

Next Deadline: YP 2.8 Milestone 2 Cutoff July 14th, 2019

Quoted 8 lines

SWAT Team Rotation:

* SWAT lead is currently: Ross
* SWAT team rotation: Ross -> Amanda on June 28, 2019
* SWAT team rotation: Amanda -> Chen on July, 5, 2019

So how do we handle holiday coverage? July 4th is a US holiday.

- armin

Quoted 100 lines

*
* https://wiki.yoctoproject.org/wiki/Yocto_Build_Failure_Swat_Team

Next Team Meetings:

* Bug Triage meeting Thursday June 27th at 7:30am PDT

    (https://zoom.us/j/454367603)
  * Monthly Project Meeting Tuesday July 2nd at 8am PDT
    (https://zoom.us/j/990892712) <https://zoom.us/j/990892712> 

* Twitch - Next event is Tuesday 9th July at 8am PDT
(https://www.twitch.tv/yocto_project)

Key Status/Updates:

* 2.8 M1 has been released.
* Mailing lists issues are continuing to be worked on as a top priority.
* We have a new “newcomer” bug category which are bugs suited to someone new to the project. These can be seen here:
https://wiki.yoctoproject.org/wiki/Bug_Triage#Newcomer_Bugs
* Several key reproducibility fixes have merged, thanks Joshua!
* The autobuilder has suffered stability issues with its NFS setup, seemingly related to the increased load from the new servers. We’re monitoring changes, hoping they fix the issue.
* We had significant problems with the versioning of libcrypt in recent distros which resulted in the need for a new uninative release. This fixes autobuilder builds.

Planned Releases for YP 2.8:

* M2 Cutoff 14th July
* M2 Release 26th July
* M3 Cutoff (Feature Freeze) 25th Aug
* M3 Release 6th Sept
* M4 Cutoff 30th Sept
* 2.8 (M4) Final Release 25th Oct

Planned upcoming dot releases:

* YP 2.7.1 (Warrior) is planned for build imminently now that 2.8 M1 is done but is pending the new uninative changes.
* YP 2.6.3 (Thud) is intended for build after 2.7.1 is complete and

    before 2.8 M2

Tracking Metrics:

* WDD 2482 (last week

    2479)(https://wiki.yoctoproject.org/charts/combo.html)

* Poky Patch Metrics
o Total patches found: 1509 (last week 1511)
o Patches in the Pending State: 638 (42%) [last week 641 (43%)]

Key Status Links for YP:

https://wiki.yoctoproject.org/wiki/Yocto_Project_v2.8_Status

https://wiki.yoctoproject.org/wiki/Yocto_2.8_Schedule

https://wiki.yoctoproject.org/wiki/Yocto_2.8_Features

The Status reports are now stored on the wiki at:
https://wiki.yoctoproject.org/wiki/Weekly_Status

[If anyone has suggestions for other information you’d like to see on this weekly status update, let us know!]

Thanks,

*/Stephen K. Jolley/**//*

*Yocto Project Project Manager*

(    *Cell*:                (208) 244-4460

* *Email*:              [email protected]
<mailto:[email protected]>_